Georgia Mechanics Lien Laws

Subs and suppliers must send Notice to Contractor within 30 days of first work. Lien must be verified before a notary and attested by 2 witnesses. 90 days from last work. 1 year to enforce.

Key Facts

Filing deadline90 days from last work
Preliminary notice requiredYes — within 30 days of first work
Notarization requiredYes
Witnesses requiredYes
Filed withSuperior Court Clerk
Typical filing fee$25–$60
Enforcement deadline12 months after filing

Step-by-step guide for Georgia

  1. 1

    Confirm your lien rights

    Verify you hold a valid contract, are properly licensed (if Georgia requires it), and that the work was on private property. Public projects require a payment bond claim, not a lien.

  2. 2

    Send preliminary notice within 30 days of first work

    Georgia requires a preliminary notice within 30 days of first furnishing labor or materials. Missing this notice permanently bars your lien rights.

  3. 3

    Track your deadline from last day of work

    Your lien must be recorded within 90 days of your last furnishing of labor or materials. Mark the calendar the day you finish work — this clock does not stop.

  4. 4

    Prepare the lien document

    Your lien claim must include: claimant name and address, property owner name, property description (legal description or address), amount claimed, description of labor/materials, and dates of first and last furnishing.

  5. 5

    Notarize the lien (required in this state)

    Georgia requires the lien to be notarized before recording. Two witnesses are also required. Use an in-person notary or an online notarization service.

  6. 6

    File with the Superior Court Clerk

    Record your lien with the Superior Court Clerk in the county where the property is located. Filing fee is typically $25–$60. Request a file-stamped copy for your records.

  7. 7

    Serve a copy on the property owner

    Most states require you to mail or personally serve a copy of the filed lien on the property owner within a short window of recording. Check Georgia rules for exact timing and method of service.

  8. 8

    Enforce by month 12

    If the debt remains unpaid, you must file a lawsuit to foreclose on the lien within 12 months of recording. If you miss this deadline, the lien expires and the cloud on title is removed without payment.