Oregon Mechanics Lien Laws

Notice of Right to a Lien required within 8 business days of first furnishing (for those not in direct contract with owner). 75 days from last work. Remarkably long 10-year enforcement window.

Key Facts

Filing deadline75 days from last work
Preliminary notice requiredYes — within 8 days of first work
Notarization requiredNo
Witnesses requiredNo
Filed withCounty Clerk
Typical filing fee$31–$75
Enforcement deadline120 months after filing

Step-by-step guide for Oregon

  1. 1

    Confirm your lien rights

    Verify you hold a valid contract, are properly licensed (if Oregon requires it), and that the work was on private property. Public projects require a payment bond claim, not a lien.

  2. 2

    Send preliminary notice within 8 days of first work

    Oregon requires a preliminary notice within 8 days of first furnishing labor or materials. Missing this notice permanently bars your lien rights.

  3. 3

    Track your deadline from last day of work

    Your lien must be recorded within 75 days of your last furnishing of labor or materials. Mark the calendar the day you finish work — this clock does not stop.

  4. 4

    Prepare the lien document

    Your lien claim must include: claimant name and address, property owner name, property description (legal description or address), amount claimed, description of labor/materials, and dates of first and last furnishing.

  5. 5

    Notarization (not required in this state)

    Oregon does not require notarization.

  6. 6

    File with the County Clerk

    Record your lien with the County Clerk in the county where the property is located. Filing fee is typically $31–$75. Request a file-stamped copy for your records.

  7. 7

    Serve a copy on the property owner

    Most states require you to mail or personally serve a copy of the filed lien on the property owner within a short window of recording. Check Oregon rules for exact timing and method of service.

  8. 8

    Enforce by month 120

    If the debt remains unpaid, you must file a lawsuit to foreclose on the lien within 120 months of recording. If you miss this deadline, the lien expires and the cloud on title is removed without payment.