Washington Mechanics Lien Laws

Contractor pre-lien notice (Notice to Customer) required within 60 days of first furnishing. 90 days from last work. 8 months to enforce after filing.

Key Facts

Filing deadline90 days from last work
Preliminary notice requiredYes — within 60 days of first work
Notarization requiredNo
Witnesses requiredNo
Filed withCounty Auditor
Typical filing fee$73–$100
Enforcement deadline8 months after filing

Step-by-step guide for Washington

  1. 1

    Confirm your lien rights

    Verify you hold a valid contract, are properly licensed (if Washington requires it), and that the work was on private property. Public projects require a payment bond claim, not a lien.

  2. 2

    Send preliminary notice within 60 days of first work

    Washington requires a preliminary notice within 60 days of first furnishing labor or materials. Missing this notice permanently bars your lien rights.

  3. 3

    Track your deadline from last day of work

    Your lien must be recorded within 90 days of your last furnishing of labor or materials. Mark the calendar the day you finish work — this clock does not stop.

  4. 4

    Prepare the lien document

    Your lien claim must include: claimant name and address, property owner name, property description (legal description or address), amount claimed, description of labor/materials, and dates of first and last furnishing.

  5. 5

    Notarization (not required in this state)

    Washington does not require notarization.

  6. 6

    File with the County Auditor

    Record your lien with the County Auditor in the county where the property is located. Filing fee is typically $73–$100. Request a file-stamped copy for your records.

  7. 7

    Serve a copy on the property owner

    Most states require you to mail or personally serve a copy of the filed lien on the property owner within a short window of recording. Check Washington rules for exact timing and method of service.

  8. 8

    Enforce by month 8

    If the debt remains unpaid, you must file a lawsuit to foreclose on the lien within 8 months of recording. If you miss this deadline, the lien expires and the cloud on title is removed without payment.